Schedule

So, this is the tentative schedule.  So far this spring we have had great weather, but you never know if that will hold.   W



Projected


Actual

Start Date
3/8/12



Footing Insp
3/11/12    
3/21/12 

Waterproof Insp
3/16/12
3/29/12


Slab Inspection
3/20/12
4/4/12


Frame/Heat/ElectInsp
4/19/12
4/27/12


Plumbing Final Insp
5/28/12



Final Inspection
5/28/12



Cert of Occ
6/01/12










85d






  • My current (April 4th) best estimate is ~ June 15th closing.  It appears the permit screwups in the beginning cost us a good 2 weeks.   Supposedly they can make up the time, but I am skeptical... Unless somehow they can get a months worth of work done in the next 15 days to get on target for the framing inspection. 
  • I am now guessing Final Inspection on 6/1 and closing on the week of the 4th.   THey have made up time on framing, but electricians cost the PM a few days.   Currently (4/25/12) they are about 7 days off schedule.   Maybe they can make up time on the inside.  
  • As of 4/30/12 PM is saying final walk through on the 6/7/12 and closing on the 8th.   That puts cert of Occupancy around the 5th.   Impressive job making up the lost time if that ends up being the case.